Kresge Update – March 26, 2020

March 26, 2020

Dear Kresge Community Members,

I hope you are all doing well as we live through the Stay in Place order from the Governor.  Our offices are still open and available to you as needed. 

Here are the latest updates on the renewal project.

Construction Updates, Activities and Impacts:
(Dates and plans are fluid and they may change)

R8 pathway – The pathway behind R8 is now open again for foot traffic.
Utility work – Porter/Kresge Road – Work Crews have marked the road to locate utilities that run underneath the road. If needed potholing will begin shortly.  The road will remain open and have traffic control staff on the road as needed.
Town Hall Complex – The Town Hall Complex demolition got delayed a week due to the weather.  Demo will begin March 30thand is scheduled to last approximately three weeks.
RNEW Residence Halls– Shotcrete work has been completed.  Concrete work is to begin soon.

If you have any questions regarding the Kresge Renewal Project please contact me.

Sincerely,

Mike Yamauchi-Gleason
Senior Director, Kresge and Porter Colleges