Rerouting electrical, fire alarm systems at Town Hall complex

February 14, 2020

Dear Kresge Community Members,

I hope your midterms have gone well. I wish you a restful three-day weekend. 

This is the latest update on the Kresge Renewal Project.

Construction Updates, Activities and Impacts:
(Dates and plans are fluid and they may change)

February 18 - You will see an increase in people walking the Kresge Site on that day. We are in the bid process for the Final Phase of the project and a number of sub-contractors will be on-site getting information in preparation to submit their bids for working on the project. Swinerton staff will be out helping direct traffic and getting the sub-contractors parked so that there is minimal traffic congestion.

Porter/Kresge Road – Safety Concerns: We still have some bicyclists using the Porter/Kresge Road from Kresge lot 145 to Heller Drive. Please stay off this road. The road is closed to all non-authorized traffic 24/7.

Water main along the Porter/Kresge Road is scheduled to be completed by the end of next week.

Shoring – Shoring systems for the project will be constructed for the next three weeks.

Town Hall Complex – Abatement of the Town Hall Complex is now completed. The next phase of work includes rerouting electrical and fire alarm systems in preparation of the demolition phase of the complex.

If you have any questions regarding the Kresge Renewal Project please contact me at myg@ucsc.edu

Sincerely,

Mike Yamauchi-Gleason
Senior Director, Kresge and Porter Colleges